How is the pre-delivery inspection of mechanical equipment conducted?

机械设备出厂前检验(FAT)六步:文件核验(合格证/认证)、外观装配检查(油漆/焊缝/泄漏)、空转试机(异响/振动/温升/安全装置)、带料试产(精度/速度/成品率达技术协议)、性能测试、签字放行(验收单+试机录像存档);带料试产是核心,合格才包装发运。

How to conduct pre-shipment inspection for machinery

The six-step process for Factory Acceptance Testing (FAT) of machinery: ① Document Verification (Certificate of Conformity, inspection records, certification); ② Appearance & Assembly (paint, welds, bolts, leak checks); ③ No-load Test Run (power-on operation: checking for abnormal noise, vibration, temperature rise, and current); ④ Trial Production with Materials (using client materials: verifying precision, speed, and yield rates); ⑤ Performance Testing (item-by-item acceptance based on technical agreements: load, precision, safety devices); ⑥ Sign-off & Release (FAT acceptance form + archived test run video; packaging and shipping occur only after passing)—pre-shipment inspection is the final quality gate before delivery.

I.
Document Verification

Certificate of Conformity (factory inspection pass); Inspection Records (critical component testing/assembly records); Certification (CE/ISO certificates matching the nameplate); Technical Agreement (basis for acceptance standards)—documentation first (confirm “what needs to be inspected” before proceeding).

II.
Appearance and Assembly Inspection

Appearance (paint, welds, dents/dings, rust); Assembly (bolt tightness, clearances, lubrication); Leaks (hydraulic, oil lines, pneumatic lines); Electrical (wiring standards, protective covers, grounding)—five-point visual check (appearance, assembly, leaks, electrical; most defects are revealed at this stage).

III. No-Load Test Run

Power-up (verify voltage specifications); No-load operation (check for abnormal noise, vibration, temperature rise, and current levels); Safety devices (test emergency stops and safety interlocks); Parameters (record operating parameters)—The no-load test verifies “operational status” (checking for normal function before loading materials).

IV. Trial Production with Material (Core Step)

Material loading: Conduct trial production using the client’s actual materials or simulated materials;
Acceptance: Ensure precision, speed, and yield rates meet technical agreement specifications; Records: Archive trial run data and parameters; Video: Record the entire process as evidence—Trial production with material is the core of the FAT (verifying actual performance rather than just appearance; shipment is withheld if standards are not met).

V. Sign-off and Release

Acceptance Form: FAT sign-off (attended by the buyer, agent, or third party);
Rectification: Re-inspect after addressing any identified issues (release granted only upon passing re-inspection); Packaging: Moisture-proof and shock-proof packaging following release approval; Release Letter: Authorization to ship (based on inspection report and acceptance form)—Sign-off and release signify quality confirmation (linked to the milestone for final payment prior to shipment).

For overseas buyers, the factory acceptance test (FAT) comprises five steps: documentation review, visual inspection, no-load test run, trial production with material, and sign-off/release.
Key safeguards include trial production with material, video documentation, and third-party attendance;
final payment and shipment release occur only after successful acceptance.